First Floor Update

Installation of the kiosk across from the circulation desk at central is behind schedule. There are several reasons, but a major one is a delay in approval of the shop drawings because of a reconsideration of the aluminum corner detail. Once that was settled, shop drawings were completed and approved, and the corner element ordered only to find it is out of stock; it’s typically available and in stock, we were told.

We had built in about six weeks of “overlap”, that is, time when we would have the checkout kiosk up and running  AND the current circ desk still in operation. We will shorten that time to one to two weeks and still be close to the target completion date of the end of December.

We have decided to take down the wooden partitions in the meantime and they are being taken down this morning. We had previously planned for the first floor desk staffing to end tomorrow, Oct 31, expecting the checkout units would be in place. We will hold to that timing and the first floor desk will be removed next week; we just have a delay on the checkout units. 

With the wooden partitions down but the kiosk not yet in place, there are some electrical plates on the floor where the kiosk will be that could become a trip hazard in the meantime. To avoid that happening, we’ll move some furniture there. This means you may see some furniture, plants, whatever, sitting there that looks a bit out of place. We’ll do our best to prevent a trip hazard and make it look at least OK! That seems better than bright orange cones for several weeks!

Book

Central Library Renovation
central-2009-078-160
http://www.kpl.gov/renovation/


First Floor Update

(News, Renovation) Permanent link

Installation of the kiosk across from the circulation desk at central is behind schedule. There are several reasons, but a major one is a delay in approval of the shop drawings because of a reconsideration of the aluminum corner detail. Once that was settled, shop drawings were completed and approved, and the corner element ordered only to find it is out of stock; it’s typically available and in stock, we were told.

We had built in about six weeks of “overlap”, that is, time when we would have the checkout kiosk up and running  AND the current circ desk still in operation. We will shorten that time to one to two weeks and still be close to the target completion date of the end of December.

We have decided to take down the wooden partitions in the meantime and they are being taken down this morning. We had previously planned for the first floor desk staffing to end tomorrow, Oct 31, expecting the checkout units would be in place. We will hold to that timing and the first floor desk will be removed next week; we just have a delay on the checkout units. 

With the wooden partitions down but the kiosk not yet in place, there are some electrical plates on the floor where the kiosk will be that could become a trip hazard in the meantime. To avoid that happening, we’ll move some furniture there. This means you may see some furniture, plants, whatever, sitting there that looks a bit out of place. We’ll do our best to prevent a trip hazard and make it look at least OK! That seems better than bright orange cones for several weeks!

Book

Central Library Renovation
central-2009-078-160
http://www.kpl.gov/renovation/

Posted by Ann Rohrbaugh at 11/13/2009 12:55:29 PM